 Project Timeline
The scheduled timelines for major second and third
phase activities of the project are charted below:

Project Milestones
Planning Phase: The K-61 Corridor Location and
Design Concept Study was concluded in July 2004. Listed below are project
milestones.
| Planning Phase Milestones |
Future |
In Progress |
Complete |
Develop Preliminary
Concepts August 2001-January 2002 |
|
|
X |
Community Interviews
(12 interviews) August 2001 |
|
|
X |
Telephone Survey (900
Households) September 2001 |
|
|
X |
Origin Destination
Survey September 2001 |
|
|
X |
Traffic Counts October 2001 |
|
|
X |
Complete Initial
Evaluation of Alternative Alignments February 2002-May 2002 |
|
|
X |
Refine Alternative
Alignments to Most Viable May 2002-December
2002 |
|
|
X |
Drop-In Centers December 2001, April 2002, May 2002, September
2002 and October 2002 |
|
|
X |
Complete
Environmental Studies and Evaluation July
2001-July 2003 |
|
|
X |
Public Meeting December 2002 |
|
|
X |
Prepare Environmental
Assessment, and Location and Design Concept Report February 2003-July 2004 |
|
|
X |
Follow-up Telephone
Survey (900 Households) July 2004 |
|
|
X |
Design Phase: The Design Phase began in
January 2003 and is projected to end in February of 2009. The end product
of this phase will be a set of engineering plans needed to construct the
K-61 roadway project. Listed below is a summary of project milestones and
projected schedules.
| Design Phase Milestones |
Future |
In Progress |
Complete |
Field Survey of Corridor January 2003-August 2004 |
|
|
X |
Selection of Design Team Consultants July-August 2003 |
|
|
X |
Kitchen Table Meetings with property owners January 31 - February 4, 2005 |
|
|
X |
Preliminary Engineering and Design (Selects the actual on-ground alignment) August 2003 - May 2006 |
|
|
X |
Right of Way Verification and Appraisal June 2006 - October 2007 |
|
X |
|
Right of Way Acquisition (This is when Right of Way is purchased) February 2007 - September 2008 |
|
X |
|
Final Engineering and Design (Construction Plans Prepared) May 2006 - November 2008 |
|
X |
|
Utility Adjustments September 2008 - February 2009 |
X |
|
|
Construction Phase: The goal of this phase is
to build the roadway project. Listed below is a schedule of milestones and
projected schedules.
| Construction Phase Milestones |
Future |
In Progress |
Complete |
Project Letting
(multiple projects) February 2009 |
X |
|
|
Construction of
Projects Spring 2009 - Summer 2011 |
X |
|
|
|
 |